Question: If a resource is assigned to the work package and the work package's activities, a. then the resource has twice as much work to do
If a resource is assigned to the work package and the work package's activities, a. then the resource has twice as much work to do for the project. b. Microsoft Project is cued to assign costs and time to both the work package and the activity. c. then the activities will be completed faster. d. the project will be completed under budget and within the schedule
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
