Question: If a specific future event terminates a party's obligations under a contract, that future event is called a(n): foreseeable event continuing condition avoidable condition condition
If a specific future event terminates a party's obligations under a contract, that future event is called a(n): foreseeable event continuing condition avoidable condition condition subsequent
Step by Step Solution
There are 3 Steps involved in it