Question: If a task had a cost variance (CV) = 150 and a schedule variance (SV) = -150, how would that be interpreted? Over budget, ahead
If a task had a cost variance (CV) = 150 and a schedule variance (SV) = -150, how would that be interpreted? Over budget, ahead of schedule Under budget, ahead of schedule Over budget, behind schedule Under budget, behind schedule On budget, on schedule