Question: If activities 1 and 1 0 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at

If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $10,000 per week, which of the following options would reduce the project duration by four weeks?