Question: If Activity 5 ( Install Raw Water Mains ) does not start until day 5 6 , then what issue ( s ) would this
If Activity Install Raw Water Mains does not start until day then what issues would this create?
Group of answer choices
If only excavator is available, then the project duration will increase
If only excavator is available, then the project duration will not increase
Delaying this activity cannot affect project duration in anyway since it is not on the critical path
The project will finish ahead of schedule
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
