Question: If an activity has three immediate predecessors and their early finish times are 1 5 , 1 5 , and 1 6 , respectively, then

If an activity has three immediate predecessors and their early finish times are 15,15, and 16, respectively, then the early start time of that activity should be:
Group of answer choices
19
16
15
cannot be determined from this information