Question: If an activity whose normal duration is 1 3 days can be shortened to 1 0 days for an added c of $ 1 ,

If an activity whose normal duration is 13 days can be shortened to 10 days for an added c of $1,500, the crash cost per period is:a) $500b) $1,500c) $750d) $13,000e) $15,000