Question: if an activity whose normal duration is 1 8 weeks can be shortened to 1 4 weeks for an added cost of 5 0 0

if an activity whose normal duration is
1
8
weeks can be shortened to
1
4
weeks for an added cost of
5
0
0
0
what is the crash cost per period 1250,357.1,20000,1000,5000