Question: If any task on a project's critical path increases, this means...? a. Answers: The Program Manager must re-baseline the whole program. b. The total project


If any task on a project's critical path increases, this means...? a. Answers: The Program Manager must re-baseline the whole program. b. The total project will also increase in length. C. There has been a breach of the acquisition program baseline. d. Hardware risk has been mitigated