Question: If earned value = 500, planned value = 700, and actual costs = 450, calculate the schedule variance. This type of question contains radio buttons

If earned value = 500, planned value = 700, and actual costs = 450, calculate the schedule variance. This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. option A 200 option B -200 option C -50 option D 50