Question: If EV = $100, AC = $90, PV = $110 and BAC = $400, how much is the Cost Variance of a project? Select one:

If EV = $100, AC = $90, PV = $110 and BAC = $400,
If EV = $100, AC = $90, PV = $110 and BAC = $400, how much is the Cost Variance of a project? Select one: O a. $40 O b. $20 O c. $300 O d. $10