Question: If not enough resources are available for a project, to maintain the same project scope and budget, the project team should Accelerate the activities that
If not enough resources are available for a project, to maintain the same project scope and budget, the project team should Accelerate the activities that have enough resources to free the needed resources. Delay some activities until the resource is available. Hire additional resources. Start the tasks on the day they are scheduled to start and expect unassigned resources from other activities to complete the work.