Question: If PV = $211, EV = $180 and AC = $212, the status is: (a) Under budget and behind schedule (b) Over budget and behind

If PV = $211, EV = $180 and AC = $212, the status is:

(a) Under budget and behind schedule

(b) Over budget and behind schedule

(c) Under budget and ahead of schedule

(d) Over budget and ahead of schedule