Question: If PV = $211, EV = $180 and AC = $212, the status is: (a) Under budget and behind schedule (b) Over budget and behind
If PV = $211, EV = $180 and AC = $212, the status is:
(a) Under budget and behind schedule
(b) Over budget and behind schedule
(c) Under budget and ahead of schedule
(d) Over budget and ahead of schedule