Question: If schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 1.0: Select one: a. Project is ahead of schedule and on budget
If schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 1.0:
Select one:
a.
Project is ahead of schedule and on budget
b.
Project is on schedule and over budget
c.
Project is behind schedule and under budget
d.
Project is behind schedule and on budget