Question: If the BAC = 5 0 0 , 0 0 0 , E V = 3 0 0 , 0 0 0 , and A

If the BAC=500,000,EV=300,000, and AC=350,000, what is the approximate expected total cost of the project work?
 If the BAC=500,000,EV=300,000, and AC=350,000, what is the approximate expected total