Question: If the cycle time is 57.6 seconds and A is assigned as the first task in Workstation #1, what is the idle time after assigning

If the cycle time is 57.6 seconds and A is

If the cycle time is 57.6 seconds and A is assigned as the first task in Workstation #1, what is the idle time after assigning task A? Number of Following Task Task Time (seconds) Tasks That Must Precede Other Tasks Tasks TA 28 7 B 13 8 C 35 B. U 6 E 20 6 TI 6 D, E 5 G 23 F 3 25 - 2 HT 37 1 J 11 GH 27 1 0 Total 236 0 26.7 minutes 0 29.6 seconds 0 57.6 seconds 0 28 seconds 0 34.5 seconds