Question: If the cycle time is 57.6 seconds and A is assigned as the first task in Workstation #1, what is the idle time after assigning

If the cycle time is 57.6 seconds and A is assigned as the first task in Workstation #1, what is the idle time after assigning task A?

Task

Task Time (seconds)

Tasks That Must Precede Other Tasks

Number of Following Tasks

A

28

-

7

B

13

-

8

C

35

B

7

D

11

A

6

E

20

C

6

F

6

D, E

5

G

23

F

3

H

25

F

2

I

37

G

1

J

11

G, H

1

K

27

I, J

0

Total

236

Group of answer choices

28 seconds

34.5 seconds

57.6 seconds

29.6 seconds

26.7 minutes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!