Question: If the direct labor hour method is used in applying factory overhead and the predetermined rate is $10 an hour, what amount should be charged

  1. If the direct labor hour method is used in applying factory overhead and the predetermined rate is $10 an hour, what amount should be charged to Job 2010 for factory overhead? Assume that direct materials used totaled $5,000, the direct labor cost totaled $3,200 and the number of direct labor hours totaled 250.