Question: If the direct labor hours needed to complete a unit of product will decrease by 20% each time the production quantity is doubled and if

If the direct labor hours needed to complete a unit of product will decrease by 20% each time the production quantity is doubled and if the direct labor hours required to complete the first unit is 100, then the number of direct labor hours required to complete the fifth unit is