If the highest priority is to minimize the average job lateness, then the job sequence should begin
Fantastic news! We've Found the answer you've been seeking!
Question:
If the highest priority is to minimize the average job lateness, then the job sequence should begin with those jobs requiring:
a. the shortest processing time.
b. the smallest critical ratio.
c. the least remaining operations.
d. the longest processing time.