Question: If the implementation costs greatly exceed the expected cost, the firm may have not done an appropriate job assessing which type of risk? Multiple Choice
If the implementation costs greatly exceed the expected cost, the firm may have not done an appropriate job assessing which type of risk?
Multiple Choice
-
Financial Risk.
-
Cost Risk.
-
Implementation Risk.
-
Technological Risk.