Question: If the optimistic completion time for a project activity is 15 hours, most likely is 20 hours and the most pessimistic is 50 hours, what

If the optimistic completion time for a project activity is 15 hours, most likely is 20 hours and the most pessimistic is 50 hours, what would be the calculated activity duration using a beta estimate rounded to the nearest whole number?

20

Insufficient information

24

28