Question: if the optimistic duration for an activity is 3 days, the most likely duration is 5 days, and the pessimistie duration is 7 days, then:

if the optimistic duration for an activity is 3
if the optimistic duration for an activity is 3 days, the most likely duration is 5 days, and the pessimistie duration is 7 days, then: a. The most likely duration and the expected duration are equal. b. The expected duration is larger than the most likely duration c. The expected duration is less than the most likely duration

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock