Question: If the optimistic estimate for a task is 12 days, pessimistic is 18 days and the most likely is 14 days what is the

If the optimistic estimate for a task is 12 days, pessimistic is

If the optimistic estimate for a task is 12 days, pessimistic is 18 days and the most likely is 14 days what is the PERT estimatg? O a 171/3days O b. 141/3 days Oc 16 2/3 days O d. 15 2/3 days

Step by Step Solution

3.37 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

14 days to optimistic time 12 days t... View full answer