Question: You use a three-point estimate for activity duration estimating. An activity has a duration of 9 days for an optimistic scenario, 18 days for a

You use a three-point estimate for activity duration estimating. An activity has a duration of 9 days for an optimistic scenario, 18 days for a pessimistic scenario, and 12 days for the most likely scenario.Which of the following will you take as the duration estimate for this activity if you use the PERT analysis?

A. 13 days B. 12.5 days C. 12 days D. 18 days