Question: If the optimistic, pessimistic, and most likely durations for a task are 4 , 1 0 , and 6 days respectively, what is the expected
If the optimistic, pessimistic, and most likely durations for a task are and days respectively, what is the expected duration in PERT?
A days
B days
C days
D days
Select the correct response:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
