Question: If the optimistic, pessimistic, and most likely durations for a task are 4 , 1 0 , and 6 days respectively, what is the expected

If the optimistic, pessimistic, and most likely durations for a task are 4,10, and 6 days respectively, what is the expected duration in PERT?
(A)6.67 days
(B)7 days
(C)6.33 days
(D)5 days
Select the correct response: