Salem Daughters Construction Company has contracted with a Mr. Hawthorne to build a classic house having...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Salem Daughters Construction Company has contracted with a Mr. Hawthorne to build a classic house having seven gables. The customer wants to complete the house as soon as possible, at a minimum cost. The preliminary data in Table 19-14 apply for the various activities. Table 10-14 Data for the Construction Activities 10000 Jas the Excavate (c) (d) (e) C (8) Activity Floor joists Exterior plumbing (6) Floor (M) Power on (2) Walls (₂) Wire (A) Comline (1) (n) (0) (0) (0) in (5) (0) Basement Foundation Inside plumbing dows Doors Sheetrock Interior trim Exterior trim Paint Carpet Buyer inspection Activity Cost $1.000 2.500 4,400 5.500 2,000 Temecatays Preceding Activity Activity Cost $ 500 3,000 & h a.c d Samantha Salem believes that the data in Table 19-14 reflect optimal expen- ditures of labor and resources. The following cost estimates correspond. 500 4,000 2.300 A.C 0,1 no m. p. g. Ex Completion T Activity Cost $200 1,500 2,300 1.000 3,200 7 m n 0 Activity Cost $8,000 3,000 3,000 5,000 0 d F Q The preceding includes the cost of materials supplied by subcontractors. Ad- ditional Salem materials costs are $51,000. A few activities can be speeded up. By working extended hours, carpenters can complete the walls in 8 days at a total cost of $4,500. Working at night,work- ers can complete the sheetrock in 2 days at a total cost of $3,500. For a premium of $700, the plumbing contractor can complete inside plumbing in 3 days. Using night lighting, crews can finish the excavation in 2 days at a total cost of $3,500 and complete the grading in 2 days for $1,600. SE 1. Construct a PERT network for the project, entering the expected activity completion times alongside the applicable arrows. 2. For each event, find the earliest possible, latest allowable, and slack times. Then, establish the critical path. How long is the project expected to take? 3. Determine a sequence of plans for Salem Daughters Construction Company, each plan representing a 1-day savings in project completion time at a mini- mal increase in cost. 4. Salem has accepted an incentive clause which provides for a payment of $400 for each day saved from an anticipated 40-day duration until project completion. Which plan identified in Question 3 should be implemented? Specify which activities should be speeded up and by how many days. What is Salem's net project cost using the optimal plan? 5. Analysis in Questions 1-4 has all been based on expected activity comple- tion times. Samantha is concerned that the uncertainties in the project have so far been downplayed. The expected activity completion times given ear- lier were computed from the three time estimate data (in days) given in Table 19-15. Compute the variance in completion time for each activity. 6. The modified beta distribution for each activity time (1) is positively skewed if m is closer to a than to b, (2) is symmetrical if m falls midway between a and b. (3) is negatively skewed if m is closer to & than to a, and (4) has zero variance if a, m, and bare all equal. (a) Determine for each activity which case applies. (b) For the zero-variance activity times, what may you conclude regarding the completion time probabilities? 7. Consider the critical path found in Question 2. (a) Find the variance for the duration of that path. (b) Determine the probability that the path will take more than 42 days. Tubio US Three Time Estimate Data for the Construction Activities Activity Orade (Excavate (c) Basement (0) Foundation fet Floor joists (f) Exterior plumbing Floor Power on Walls (Wire (K) Com lines Un Inside plumbing um Windows Doors to) Shoetrock (p) Interior trim. (0) Extenor trim (Paint (5) Carpet (t) Buyer inspection Optimistic Most Likely Time Time 5.25 3 4.75 4 1 Pessimistic Time 8. Consider the "nearly" critical path b-cd-e-gi-j-k-op-rs-t (a) Find the expected duration and variance of that path. 10 NANNA 55 (b) Determine the probability that the path will take more than 42 days. (c) Compare your answers in Question 7(b). What may you conclude re- garding using any single-path probability to estimate a probability for project completion time? Salem Daughters Construction Company has contracted with a Mr. Hawthorne to build a classic house having seven gables. The customer wants to complete the house as soon as possible, at a minimum cost. The preliminary data in Table 19-14 apply for the various activities. Table 10-14 Data for the Construction Activities 10000 Jas the Excavate (c) (d) (e) C (8) Activity Floor joists Exterior plumbing (6) Floor (M) Power on (2) Walls (₂) Wire (A) Comline (1) (n) (0) (0) (0) in (5) (0) Basement Foundation Inside plumbing dows Doors Sheetrock Interior trim Exterior trim Paint Carpet Buyer inspection Activity Cost $1.000 2.500 4,400 5.500 2,000 Temecatays Preceding Activity Activity Cost $ 500 3,000 & h a.c d Samantha Salem believes that the data in Table 19-14 reflect optimal expen- ditures of labor and resources. The following cost estimates correspond. 500 4,000 2.300 A.C 0,1 no m. p. g. Ex Completion T Activity Cost $200 1,500 2,300 1.000 3,200 7 m n 0 Activity Cost $8,000 3,000 3,000 5,000 0 d F Q The preceding includes the cost of materials supplied by subcontractors. Ad- ditional Salem materials costs are $51,000. A few activities can be speeded up. By working extended hours, carpenters can complete the walls in 8 days at a total cost of $4,500. Working at night,work- ers can complete the sheetrock in 2 days at a total cost of $3,500. For a premium of $700, the plumbing contractor can complete inside plumbing in 3 days. Using night lighting, crews can finish the excavation in 2 days at a total cost of $3,500 and complete the grading in 2 days for $1,600. SE 1. Construct a PERT network for the project, entering the expected activity completion times alongside the applicable arrows. 2. For each event, find the earliest possible, latest allowable, and slack times. Then, establish the critical path. How long is the project expected to take? 3. Determine a sequence of plans for Salem Daughters Construction Company, each plan representing a 1-day savings in project completion time at a mini- mal increase in cost. 4. Salem has accepted an incentive clause which provides for a payment of $400 for each day saved from an anticipated 40-day duration until project completion. Which plan identified in Question 3 should be implemented? Specify which activities should be speeded up and by how many days. What is Salem's net project cost using the optimal plan? 5. Analysis in Questions 1-4 has all been based on expected activity comple- tion times. Samantha is concerned that the uncertainties in the project have so far been downplayed. The expected activity completion times given ear- lier were computed from the three time estimate data (in days) given in Table 19-15. Compute the variance in completion time for each activity. 6. The modified beta distribution for each activity time (1) is positively skewed if m is closer to a than to b, (2) is symmetrical if m falls midway between a and b. (3) is negatively skewed if m is closer to & than to a, and (4) has zero variance if a, m, and bare all equal. (a) Determine for each activity which case applies. (b) For the zero-variance activity times, what may you conclude regarding the completion time probabilities? 7. Consider the critical path found in Question 2. (a) Find the variance for the duration of that path. (b) Determine the probability that the path will take more than 42 days. Tubio US Three Time Estimate Data for the Construction Activities Activity Orade (Excavate (c) Basement (0) Foundation fet Floor joists (f) Exterior plumbing Floor Power on Walls (Wire (K) Com lines Un Inside plumbing um Windows Doors to) Shoetrock (p) Interior trim. (0) Extenor trim (Paint (5) Carpet (t) Buyer inspection Optimistic Most Likely Time Time 5.25 3 4.75 4 1 Pessimistic Time 8. Consider the "nearly" critical path b-cd-e-gi-j-k-op-rs-t (a) Find the expected duration and variance of that path. 10 NANNA 55 (b) Determine the probability that the path will take more than 42 days. (c) Compare your answers in Question 7(b). What may you conclude re- garding using any single-path probability to estimate a probability for project completion time?
Expert Answer:
Answer rating: 100% (QA)
Finding earliest possible latest allowable and slack times To find the earliest possible latest allowable and slack times we perform forward and backward pass calculations Forward pass earliest possib... View the full answer
Related Book For
Business Statistics a decision making approach
ISBN: 978-0133021844
9th edition
Authors: David F. Groebner, Patrick W. Shannon, Phillip C. Fry
Posted Date:
Students also viewed these accounting questions
-
The U.S. Army Corps of Engineers has contracted with a medium-size excavation firm to construct a small series of three earthen dams as part of a flood control project in North Carolina. For economic...
-
The Minnesota State Fishing Bureau has contracted with a university biologist to study the length of walleyes (fish) caught in Minnesota lakes. The biologist collected data on a sample of 1,000 fish...
-
The Record-a-Song Company has contracted with a rising star to record eight songs. The durations of the different songs are 8,3,5,5,9,6,7, and 12 minutes, respectively. Recorda- Song uses a two-sided...
-
Design a suitable angle section to carry a factored tensile force 210 kN assuming a single row of M20 bolts. The yield strength and ultimate strength of the material is 250 MPa and 410 MPa,...
-
Organic chemists often purify organic compounds by a method known as fractional crystallization. One chemist prepared ten 4.85-g quantities of aniline and purified it to acetanilide. The following...
-
During a routine medical checkup, Shelby, a 26-year-old physiotherapy student, is surprised to hear that her blood pressure is 180/110. She also has a rumbling systolic and diastolic abdominal bruit...
-
Give three specialized subclasses for the Student class.
-
A graphical approach was used to solve the following LP model in Problem 2-14: Maximize profit = $4X + $5T Subject to the constraints 20
-
Select a metallic ship or boat component that is manufactured starting from a billet using at least two combinations of forging, rolling, extrusion or wire drawing (ex. Hot extrusion then forging). ...
-
Force on a surface of arbitrary orientation? (Figure 1D.2) Consider the material within an element of volume OABC that is in a state of equilibrium, so that the sum of the forces acting on the...
-
The Wreight Company deposits all its cash receipts on the day that they are received and makes all cash payments in the form of checks. You are not being asked to complete a Bank Reconcilement, but...
-
Evaluate each expression in Problems 3-32. \({ }_{12} P_{5}\)
-
In how many ways can three hearts be drawn from a deck of cards?
-
Evaluate each expression in Problems 3-32. \({ }_{52} P_{3}\)
-
For the system shown in Fig. P2.7, determine characteristic equation. Hence find the following when excitation is a unit step ; (a) undamped natural frequency (b) damped frequency of oscillation (c)...
-
The forward transfer function of a unity feedback type 1, second order system has a pole at \(s=-3\). The gain \(k\) is adjusted for the damping ratio of 0.6 . Compute steady state error if this...
-
Use the data in exhibits 10 to 14 to calculate a discount rate for valuing the cost savings. Explain and defend your choice of beta and the risk free rate and market risk premium. here goes exhibits...
-
Refer to the situation described inBE 18-13, but assume a 2-for-1 stock split instead of the 5% stock dividend. Prepare the journal entry to record the stock split if it is to be effected in the form...
-
The Sunbeam Corporation makes a wide variety of appliances for the home. One product is a digital blood pressure gauge. For obvious reasons, the blood pressure readings made by the monitor need to be...
-
Boston Properties is a real estate investment trust (REIT) that owns first-class office properties in selected markets. According to its 2010 annual report, its percentage of net operating income...
-
The Oasis Chemical Company develops and manufactures pharmaceutical drugs for distribution and sale in the United States. The pharmaceutical business can be very lucrative when useful and safe drugs...
-
The isotope cesium-137, which has a half-life of 30 years, is a product of nuclear power plants. How long will it take for this isotope to decay to about one-half its original amount? (a) 0 yr (b) 15...
-
Which of the three raysalpha, beta, or gammahas the greatest penetrating power?
-
Which type of radiationalpha, beta, or gammaresults in the greatest change in mass number? The greatest change in atomic number?
Study smarter with the SolutionInn App