Question: If the optimistic time for an activity is 3, the most likely time for the activity is 5 and the pessimistic time for the activity

If the optimistic time for an activity is 3, the most likely time for the activity is 5 and the pessimistic time for the activity is 7, what is the expected time for the activity? (Round your answer to six-decimal place accuracy only if necessary