Question: If the project completion time is normally distributed and the due date for the project is greater than the expected completion time, then the probability

If the project completion time is normally distributed and the due date for the project is greater than the expected completion time, then the probability that the project will be finished by the due date is:Single choice.

(2 Points)

Equal to zero.

Equal to 0.50.

Less than 0.50.

Greater than 0.50.

Undeterminable without more information.