Question: In a simple CPM Project network, three tasks A, B and C must be completed. A must be completed before B and B must be

In a simple CPM Project network, three tasks A, B and C must be completed. A must be completed before B and B must be completed before beginning task C. A's single task time estimate =5; B's single task time estimate =10;C s single task time estimate =7. Which of the following statements is true? The project completion time is normally distributed. The project completion time is 17. The project completion time is 12 . The project completion time is 22