Question: If the second sub-project's start is not brought earlier by two weeks and overtime and afterhours work are forbidden for the programme, what else could
If the second sub-project's start is not brought earlier by two weeks and overtime and afterhours work are forbidden for the programme, what else could Louise propose to meet the deadline of 30 November and satisfy all other terms of the big deal? In other words, the contract is immutable and the programme must be balanced at the project level. Briefly explain how this might work with reference to the scenario