Question: If there is a change order which affects the cost or time of the subcontract work, and the GC and the subcontractor cannot reach an

If there is a change order which affects the cost or time of the subcontract work, and the GC and the subcontractor cannot reach an agreement about the additional price with in ten days, the subcontractor should
proceed with the work according to the changed design
contact the owner immediately
file a law suit against the general contractor
wait until an agreement on the cost
 If there is a change order which affects the cost or