Question: If this factory transitioned from a batch manufacturing process to single piece flow, what would be the improvement in throughput time? Workstation Batch Size (Q)

If this factory transitioned from a batch manufacturing process to single piece flow, what would be the improvement in throughput time?

Workstation Batch Size (Q) Processing Time per Item
A 50 10 seconds
B 50 55 seconds
C 50 30 seconds
D 50 5 seconds

answer of choices

Not enough info

53.1%

44.4%

46.9%

52.3%

_________________________________________________________________________

The Production Supervisor for a Manufacturing firm is planning the production of two electronic devices: Radios (R) and Sensors (S). Profits for the Radios are $8.00 per unit, and profits for the Sensors are $4.00 per unit. Two resources are constrained: production time (T), of which he has at most 160 minutes per day; and electronics (E), of which he can get at most 380 minutes per day. To build a Radio requires 2 minutes of production time and 5 minutes of electronics time, and to build a Sensor it requires 4 minutes of production time and 8 minutes of electronics time.

Using the Algebraic Method, calculate the Optimal Daily Profits.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!