Question: If this factory transitioned from a batch manufacturing process to single piece flow, what would be the improvement in throughput time? Workstation Batch Size (Q)
If this factory transitioned from a batch manufacturing process to single piece flow, what would be the improvement in throughput time?
| Workstation | Batch Size (Q) | Processing Time per Item |
| A | 50 | 10 seconds |
| B | 50 | 55 seconds |
| C | 50 | 30 seconds |
| D | 50 | 5 seconds |
answer of choices
Not enough info
53.1%
44.4%
46.9%
52.3%
_________________________________________________________________________
The Production Supervisor for a Manufacturing firm is planning the production of two electronic devices: Radios (R) and Sensors (S). Profits for the Radios are $8.00 per unit, and profits for the Sensors are $4.00 per unit. Two resources are constrained: production time (T), of which he has at most 160 minutes per day; and electronics (E), of which he can get at most 380 minutes per day. To build a Radio requires 2 minutes of production time and 5 minutes of electronics time, and to build a Sensor it requires 4 minutes of production time and 8 minutes of electronics time.
Using the Algebraic Method, calculate the Optimal Daily Profits.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts