Question: If we don't define the critical path: A. We may reduce cycle times of non-critical path activities, which won't have as much an impact on
If we don't define the critical path:
A. We may reduce cycle times of non-critical path activities, which won't have as much an impact on total cycle time
B. for processes, we can't effectively reduce defect levels
C. We may reduce cycle times of non-critical path activities, which will have NO impact on total cycle time.
D. All of the above.