Question: If we don't define the critical path: for processes, we can't effectively reduce defect levels. we may reduce cycle times of non - critical path

If we don't define the critical path:
for processes, we can't effectively reduce defect levels.
we may reduce cycle times of non-critical path activities, which won't have as much an impact on total cycle time.
we may reduce cycle times of non-critical path activities, which will have no impact on total cycle time.
All of the above.