Question: If we want to save time and work on decreasing the total duration of a project, we can do the following: 1 point Invest more

If we want to save time and work on decreasing the total duration of a project, we can do the following: 1 point Invest more resources on either critical or noncritical activities. Ask our labors to come and work overtime. Focus your resources only on the critical activities