Question: Question 1 The Work Breakdown Structure is a crucial document of managing a project. Say which of the following sentences is correct. Status: [ object
Question
The Work Breakdown Structure is a crucial document of managing a project. Say which of the following sentences is correct.
Status: object Object
point
The Work Breakdown Structure is the document leveraged to manage the relationship between the Customer and the project Team.
The Work Breakdown Structure is always defined by decomposing the projects in a logical and timephased way, in order to correctly identify which departments will work earlier on the project.
The Work Breakdown Structure is composed by WBEWork Breakdown Elements, the most relevant ones are the project itself at the top the work packages at the bottom and in some cases the Control Accounts.
Question
The duration of an activity:
Status: object Object
point
is an intrinsic characteristic.
depends only by the number of people involved.
depends by who is going to perform it
Question
Considering the Gantt Chart, say which of the following sentences is correct.
Status: object Object
point
The total duration of the project is given by its critical paths
Each project has always a single critical path.
The float of a critical activity is higher than zero as it can have a certain amount of delay without impacting the project total time.
Question
Considering the planning process, say which of the following sentences is correct.
Status: object Object
point
The Duration of an activity does not depend on the quantity of resources allocated.
The Cost of an activity does not depend on the quantity of resources allocated.
Sequencing the activities is a crucial step to develop the project Schedule.
Question
Milestones are a powerful tool for planning and controlling. Say which of the following sentences is correct.
Status: object Object
point
Contractual Milestones are included into the contract, thus they do not exist for internal projects.
Using the delivery of a prototype as a milestone might be a problem, it would be more correct to put the milestone on its validation.
There is a direct correlation between the frequency of milestones and their importance. The more milestones are planned the more they are perceived as important.
Question
Considering the Float Management in the planning phase, say which of the following sentences is correct.
Status: object Object
point
In a project plan the activities must always be planned to start as soon as possible, no matter what.
The float of a noncritical activity can be partially or totally burned in the planning phase but this will increase the project risk of delay.
The Organizational Feasibility is an activity of the planning phase which checks for the organizational ability to technically develop the project.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock