Question: If you are working on a software project and the planned value of the programming activity in the project is 110,000 and the actual cost

If you are working on a software project and the
If you are working on a software project and the planned value of the programming activity in the project is 110,000 and the actual cost spent on programming was 120,000 and the earned value for this activity represents 130,000, then the cost Variance for this activity is equal to a)-10000 b)-10.000 c)20,000 d) 20,000