If you at the same time receive the recommendation of another project (Project B) from your CFO,
Fantastic news! We've Found the answer you've been seeking!
Question:
The IRR for project B is 34%. Because of capital budget restrictions, you can only select one project from the two. Let's take the Base Case of Project A for comparison.
Given the required rate of return is 20%, calculate the NPV for project B.
Based on the IRR criterion, which project will you undertake? Explain why
Based on the NPV criterion, which project will you undertake? Explain why.
In general, under what conditions the NPV and IRR may provide conflicting results?
Are the projects you undertake in (g) and (h) the same? Which project will you finally undertake? Why?
Related Book For
Fundamentals of Financial Management
ISBN: 978-0324597707
12th edition
Authors: Eugene F. Brigham, Joel F. Houston
Posted Date: