Question: If you can, please solve the problems with excel equations and make them visible please!! I'm really struggling with excel equations. Your help is much
P8-10 Assessing return and risk Swift Manufacturing must choose between two asset pur- chases. The annual rate of return and the related probabilities given in the following table summarize the firm's analysis to this point. Project 257 Rate of return Probability -10% 0.01 10 0.04 20 0.05 30 0.10 40 0.15 45 0.30 50 0.15 60 0.10 70 0.05 80 0.04 100 0.01 Project 432 Rate of return Probability 10% 0.05 15 0.10 20 0.10 25 0.15 30 0.20 35 0.15 40 0.10 45 0.10 50 0.05 a. For each project, compute: (1) The range of possible rates of return. (2) The average return. (3) The standard deviation of the returns. (4) The coefficient of variation of the returns. x Construct a bar chart of each distribution of rates of return. c. Which project would you consider less risky? Why