Question: If you have the project whose data is shown in the following table: Activity Previous Normal Downsizing Normal Downsizing Symbol Activities Time Time Cost Cost

If you have the project whose data is shown in the following table: Activity Previous Normal Downsizing Normal Downsizing Symbol Activities Time Time Cost Cost A 3 2 1000 1600 B 2 1 2000 2700 C 1 300 300 D A 7 1300 1600 F B 6 3 850 1000 F C 2 H 4000 5000 G D, E 4 2 1500 2000 1) Determine the critical path and the project implementation period 2) How much will it cost to reduce the Project Implementation Period by 3 weeks? *#Details of the answers is required