Question: If you have the project whose data is shown in the following table: Activity Previous Normal Downsizing Normal Downsizing Symbol Activities Time Time Cost Cost

 If you have the project whose data is shown in the

If you have the project whose data is shown in the following table: Activity Previous Normal Downsizing Normal Downsizing Symbol Activities Time Time Cost Cost A 3 2 1000 1600 B 2 1 2000 2700 C 1 300 300 D A 7 1300 1600 F B 6 3 850 1000 F C 2 H 4000 5000 G D, E 4 2 1500 2000 1) Determine the critical path and the project implementation period 2) How much will it cost to reduce the Project Implementation Period by 3 weeks? *#Details of the answers is required