Question: A Project plan has been developed by the project team. The scheduled data are given in the following table Activity predecessor Normal time Crash Time
A Project plan has been developed by the project team. The scheduled data are given in the following table
| Activity | predecessor | Normal time | Crash Time | Normal cost | Crash COST | COST SLOPE |
| A | - | 12 | 7 | 3000 | 5000 | 400 |
| B | A | 8 | 5 | 2000 | 3500 | 500 |
| C | A | 4 | 3 | 4000 | 7000 | 3000 |
| D | B,C | 12 | 9 | 50000 | 71000 | 7000 |
| E | B,C | 4 | 1 | 500 | 1100 | 200 |
| F | E | 4 | 1 | 500 | 1100 | 200 |
| G | D,F | 4 | 3 | 15000 | 22000 | 7000 |
Requirements:
- Find the minimum project completion time and corresponding cost.
- If the customer wants to complete the project in 30 Wks. Find the cost of the project.
- What is the minimum project completion cost and corresponding time. If indirect cost is Rs 1000 per week.