Question: If you know that the A C = 6 0 0 , P V = 5 0 0 and E V = 4 0 0

If you know that the AC=600,PV=500 and EV=400, this project is currently
budget and q, schedule.
over, ahead of
under, ahead of
under, behind
over, behind
on, on
 If you know that the AC=600,PV=500 and EV=400, this project is