Question: If you may, can you please write down how the solution would look on paper. Thank you so much! Q1: Company A needs to process

If you may, can you please write down how the solution would look on paper. Thank you so much!
Q1: Company A needs to process 3 jobs. Each job has two operations. All jobs use the printing machine first for operation 1 and then use binding machine for operation 2. (a) Using Johnson's rule to generate a schedule for both machines. (b) If job B's due date is 10, find earliness, tardiness, lateness, flow time and waiting time for Job B. Processing time Job A Job B Job C Machine Machine 1 2 2 4 7 3 5 1Step by Step Solution