Your task requires miles of paving, and it will take hours to complete one mile. On a past project similar to this one, it took hours to complete. Which of the following statements is true regarding this estimate?
A The total estimate for this task is hours, which was derived using parametric estimating.
The total estimate for this task is hours, which was derived using analogous estimating.
C The total estimate for this task is hours, which was derived using expert judgment.
The total estimate for this task is hours, which was derived using expert judgment.