Question: II . On April 1 , Owner made a contract with a contractor, an electrical contractor, to do electrical work on Owner's hotel for $
II On April Owner made a contract with a contractor, an electrical contractor, to do electrical work on Owner's hotel for $ million. A clause in the contract stated that for each day that the work was not completed, Contractor would be liable for $ per day. The contract provided that the work be done by June