Question: III A program manager [PM] is completing the Technology Maturation and Risk Reduction {THEE} Phase Request tor Proposal IRFP} package. The PM wants to make
![III A program manager [PM] is completing the Technology Maturation and](https://s3.amazonaws.com/si.experts.images/answers/2024/06/6678e35288f74_5466678e3527799d.jpg)

III A program manager [PM] is completing the Technology Maturation and Risk Reduction {THEE} Phase Request tor Proposal IRFP} package. The PM wants to make sure the Materiel Solution Analysis [MSA] Phase program protection team has completed their RFP inputs. Which of the following represent program protection RFP content? {Select the three alternatives that apply\" C] System Requirements Document [8RD] protection requirements C] Potential components list C] Statement otWork {80W} protection requirements C] Program Protection Implementation Plan [PPIP) C] DD 254 with classication indication