Question: I'm having a real hard time with this question, can some guidance be shown? 1. (a) Fill out the following MRP record for Part C.

I'm having a real hard time with this question, can some guidance be shown?I'm having a real hard time with this question,I'm having a real hard time with this question,

1. (a) Fill out the following MRP record for Part C. 1 35 | 2 40 Week 3 4 40 40 5 40 6 45 30 Part C Gross requirements Scheduled receipts Projected available balance Planned receipts Planned order releases Lot size=30, LT=1, SS=0 40 1(b) Given the above MRP record and the following routing data for Part C, determine the capacity requirements for work center 100 from Part A using CRP. For the scheduled receipt of 30 units in week 1, assume that the setup and half of the quantity have been completed. Routing Data for Part C Operation Operation 1 Set Work Center 100 Setup Time 2 hours Run Time 0.2 hour Capacity requirements for work center 100 from Part C Week | 1 | 2 | 3 4 Hours of Capacity 2. The following input/output data were gathered at the end of week 4 for a work center. Week Planned Input Actual Input Cumulative Deviation 1 60 68 2 60 70 3 60 75 4 60 70 / Planned Output Actual Output Cumulative Deviation | L 65 60 | | 65 62 | | 65 63 L 65 65 Planned Backlog 30 Actual Backlog 30 (a) Complete the input/output document. (b) What recommendations would you make

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!