Question: I'm in exam 24. Using PERT Method, what is the expected duration for an activity with the optimistic duration (minimum)=2, Most likely duration=3, and pessimistic

I'm in exam 24. Using PERT Method, what is the

I'm in exam

24. Using PERT Method, what is the expected duration for an activity with the optimistic duration (minimum)=2, Most likely duration=3, and pessimistic duration(maximum) 4?* (1.5 Points) O 12 O 6 3 o 4 2