Question: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A C, E 4 2 $2000 B A 6 2 $1000 C G 6
Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A C, E 4 2 $2000 B A 6 2 $1000 C G 6 6 N/A D C 3 2 $1000 E G 5 2 $500 F A, D 5 2 $1250 G none 5 2 $2250 *Shortest possible time for the task 1. Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task